Create Test
Quiz logo

R,B & B 501 TO 562

Created on 25th July 2025

Play

11 plays

Questions

64 Questions

No Description

Questions (64)

1. As per IRC recommendation for CBR method of design Lane distribution factor for two Lane single carriageway road is

0.75

4 choice options

2. As per IRC recommendation for CBR method of design traffic growth rate maybe considered as......... if data not available

7.50 %

4 choice options

3. As per IRC recommendations, per day number of........... is considered for pavement design by CBR method.

Commercial vehicles of gross weight 3 tonne or more

4 choice options

4. The CBR method of pavement design gives

Total thickness requirement of the Pavement above subgrade

4 choice options

5. The design CBR for payment design shall be

4 day soaked CBR of remoulded sample

4 choice options

6. Which of the following pavement composition is recommended if total pavement thickness required is 575 mm for a CBR say 5% ?

25 mm SDBC +50 mm BM +225 WBM + 275 GSB

4 choice options

7. Which of the following is an example of flexible pavement?

Bituminous pavement

4 choice options

8. What is the true for Dowel bars in cc pavement ?

Half length is bonded in CC slab and remaining is embedded in adjacent slab

4 choice options

9. In CC pavement tie bars are provided......

Across the longitudinal joints of two adjacent slabs

4 choice options

10. For compaction of non plastic silts and fine Sands......... are used.

Pneumatic tyred roller

4 choice options

11. In construction of WBM roads rolling

starts from either edge and gradually shifts towards centre

4 choice options

12. In construction of WBM roads rolling

Is done after spreading course aggregates and also after application of binding material and water

4 choice options

13. In construction of WBM roads, lateral confinement in form of shoulder.......

Is provided before coarse aggregates are spread

4 choice options

14. Soil stabilization is done to

Improve the stability or bearing power of the soil

4 choice options

15. Before filling pot holes are.......

Cut to rectangular shape and affected material is removed

4 choice options

16. The first priority of road maintenance is.......

To fill potholes

4 choice options

17. The finished level of pot hole filling is kept.....

Slightly Above original level to allow further compaction under traffic

4 choice options

18. For a bitumen hungry surface of road,

Liquid seal Coat is provided

4 choice options

19. The test validity of the statement "for wbm roads, it is necessary to replace the soil Binder periodically"

True ,it is required as rains wash out binding material and aggregates protrude out

4 choice options

20. Benkelman beam method is used

To design thickness overlay over a flexible pavement

4 choice options

21. Catch water Drains are provided.....

To intercept and divert the water from the hill slope

4 choice options

22. Drainage of rain water is important for roads....

In all types of terrains

4 choice options

23. Job mix design refers to...

Proportioning of aggregates and deciding bitumen content required

4 choice options

24. Crush metal of 25 mm size shall pass 100% through.......... square mesh and 100% Retain on........ square mesh

40mm, 20mm

4 choice options

25. Riding return is cast Monolithic with......

Solid abutment

4 choice options

26. Raft foundation for Bridge is suitable where...

Hard Strata is not available at economical depth

4 choice options

27. A bridge which never gets overtopped during floods is

High level Bridge

4 choice options

28. For solid slab Bridge upto span of 10 m,......... is used

Tar paper bearing

4 choice options

29. For submersible Bridges, following type of parapet is NOT suitable

RCC anti crash barrier

4 choice options

30. For Bridge with Rawat Foundation, flexible media consist of

900 mm thick sand filling

4 choice options

31. Length of raft slab is kept equal to......

Distance between the heels of abutment right and abutment left

4 choice options

32. Clear carriageway with of single Lane Bridge is

4.25 m

4 choice options

33. RCC wearing course is provided on deck of......

Submersible bridges

4 choice options

34. For bridge of height 8 m with hard Strata at Shallow depth which type of Return is used ?

Soild retaining walls

4 choice options

35. And is filled in box return because

It can be compacted by hand compaction as roller compaction in box return is not possible

4 choice options

36. Which of the following is NOT provided for submersible bridges

Water spouts

4 choice options

37. The foundation of pier/ abutment of bridge shall be keyed into the hard rock by

0.6 m

4 choice options

38. In inglis formula for calculation of discharge if C =7000 and A is catchment area in sq. Mile discharge is given in

Cusec

4 choice options

39. O.H.F.L in Bridge engineering stand for

Observed highest flood level

4 choice options

40. Soffit of submersible river bridge is calculated as Soffit level =

OFL + Afflux + Vertical Clearance in m.

4 choice options

41. % obstruction for bridges is Calculated on ......

Obstructed discharge Basis

4 choice options

42. Expansion joint used for solid slab Bridge with span upto 10 m, is

Pre Moulded Bituminous Pad

4 choice options

43. In Raft foundation, apron and apron wall are provided.

After casting of cut off walls but before casting raft slab

4 choice options

44. Weep Holes are provided

In abutments and Returns

4 choice options

45. In a normal slab Girder Bridge main rainforcement in the slab is provided along the......

Traffic Direction

4 choice options

46. The weight of stone to be used for apron for raft Foundation shall not be less than

40 k.g

4 choice options

47. G.A.D stands for....

General Arrangement Drawing

4 choice options

48. To calculate Scour level,......... is used

Silt Factor

4 choice options

49. As per IRC, in moderate condition concrete cover to reinforcement in pier is

40 mm

4 choice options

50. In skew river bridge, piers are oriented

Along the current Direction

4 choice options

51. The minimum vertical clearance required in the verhicular underpass with light traffic is

3.5 m

4 choice options

52. The economical span to height ratio for Bridge with open Foundation is

1.25 to 1.50

4 choice options

53. R.E. wall stands for

Reinforcement Earth wall

4 choice options

54. R.E. walls ate used for approaches of

Flyovers and ROBs

4 choice options

55. Which of the following are traffic control device ? 1. Signs. 2. Signals 3. Road marking 4. Islands

All

4 choice options

56. BBM stands for 1. Bitumen Bound Macadam 2. Burnt brick Masonry 3. Bridge Bench Mark 4. Bitumen Built Macadam

1,2

4 choice options

57. 'MSA' Stands for 1. Material at site Account 2. Maximum Size of Aggregates 3. Million Standard Axles 4. Mean Size of Aggregates

1,2,3

4 choice options

58. Which of the followings are TRUE statements ? 1. Non- Load bearing walls carry their own weight only 2. Load bearing walls carry their own weight 3. Non-Load bearing walls carry superimposed loads 4. Load bearing walls carry superimposed loads

1,2,4

4 choice options

59. The methods of soil stabilization are...... 1. mechanical soil stabilization 2. soil lime stabilization 3. soil bitumen stabilization 4. soil concrete stabilization

1,2,3

4 choice options

60. Calculate spacing of T-8 bars required to be provided for surface rainforestment of 5 kg /sq.m equally divided in both direction (rounded to lower multiply of 10)

150

4 choice options

61. Volume of wall type pier With all- round batter is calculated correctly by

Prismoidal formula = H/6 *(Atop + 4* Amid + Abot)

4 choice options

62. Which of the following statements about period of removal of formwork are true ? 1.vertical sides of slabs beams columns and walls....24-48 2. Slab soffit (with props left)........3 Days 3. Props of Slab (span upto 4.5 m ).......7 Days 4. Props of Slab (span > 4.5m ).........14 Days

All Four are True

4 choice options

63. Which of the following lists all components of the piles Foundation

Piles, pile Cap and steel liner.

4 choice options

64. Calculation volume of wall type pier with half round cut and easy water, straight length = 6.0 m, width = 1.00 m without Batter. Height = 10 m

67.85 cum

4 choice options